Road projects
State highway work under way in Bay County and what each contract costs, what the Florida Department of Transportation plans for the next five years, and the county and city road jobs paid for by the half-cent sales tax.
Who fixes which road
- The state runs the highways. State roads such as US 98, US 231, SR 77 and SR 390 belong to the Florida Department of Transportation (FDOT). Its District 3 office in Chipley plans and hires the work, mostly with state fuel tax and federal money.
- The county and cities run the rest. Neighborhood streets and county roads are theirs. Much of that paving is paid for by the half-cent infrastructure sales tax voters approved in 2016.
- The plan comes first. Each year FDOT adopts a five-year work program: a study, then design, then buying land, then construction. A project's construction year can move as money changes.
State road work under way
17 FDOT contracts, largest first- Contract under way (dot at the start of the work)
SR 30A (US98) PC BCH PKWY from E of Nautilusst to E of R Jackson BLVD - Add lanes and reconstruct
SR 30A (US 98) PC BCH PKWY from E of R Jackson BLVD to Hathaway Bridge - Add lanes and reconstruct
SR 30A (US 98) PC Beach PKWY from Mandy Lane to East of Nautilus St - Add lanes and reconstruct
SR 390 St Andrews from SR 368 23RD St to E of CR 2312 Baldwin Road - Add lanes and reconstruct
SR 20 Over Econfinacreek, Bridge No. 460037AND 460034 - Bridge replacement
SR 75 (US 231) at CR 2315 Star Ave / Titus Rd Realignment - Intersection improvement
SR 368 23RD St from SR 390 to SR 75 (US 231) - Resurfacing
SR 390 Over Mill Bayou Bridge No. 460020 - Bridge replacement
Scott's Ferry Rd Over Bear Creek Bridge No. 464419 - Bridge replacement
SR 77 from 23RD Street to CR 2312 Baldwin Road - Bike lane and sidewalk
SR 75 (US 231) at Pipeline Road Intersectionimprovements - Intersection improvement
SR 75 (US 231) at SR 20 Intersection Safety Improvements - Safety project
SR 75 (US 231) at CR 388 Intersection Improvements - Traffic signals
SR 30 (US 98) Elevated Roadway E to W of Tyndall Afb Ent Landscaping - Landscaping
SR 390 St Andrews BLVD from CR 2341 Jenks Ave to E of SR 77 Ohio Ave - Landscaping
SR 388 from SR79 to East of Nwf Beaches Int'l Airport - Landscaping
The bar under each project shows how much of the scheduled time has passed, not how much work is done. Contract amounts are the current amount of every funding line on the contract, with any changes FDOT has approved.
Coming up: FDOT's five-year work program
72 projectsSR 30A (US 98) PC Beach PKWY from Mandy Lane to East of Nautilus St
SR 30A (US98) PC BCH PKWY from E of Nautilusst to E of R Jackson BLVD
SR 30A (US 98) PC BCH PKWY from E of R Jackson BLVD to Hathaway Bridge
SR 390 St Andrews from SR 368 23RD St to E of CR 2312 Baldwin Road
SR 390 from 34TH Place to N of Jenks Ave Landscaping
SR 390 St Andrews BLVD from 23RD Street to E of CR 2312 Baldwin Road
SR 75 (US 231) from North of Pipe Line Rd to North of Penny Road
SR 75 (US 231) from SR 30A (US 98) 15TH St to South of Pipe Line Rd
SR 75 (US 231) from SR 30A (US 98) 15TH St to SR 368 23RD Street
SR 75 (US 231) from SR 368 23RD Street to North of Pipe Line Road
SR 75 (US 231) at CR 2315 Star Ave / Titus Rd Realignment
SR 392A Hutchison BLVD from SR 30 (US 98A) to SR 30 (US 98A)
SR 20 from Washington County Line to SR 75 (US 231)
SR 370 Gulf Coast Parkway from SR 30A (US 98) to CR 2315 Star Avenue
SR 390 E 14TH Street from SR 77 Ohio Avenue to SR 75 (US 231)
SR 388 from SR 79 to E of Nwf Beaches Intl Airport
Scott Road Over Econfina Creek Bridge No. 464423
SR 30 (US 98) from W of Canal PKWY to Gulf County Line
SR 30 (US 98) Elevated Roadway E to W of Tyndall Afb Entrance
SR 79 from SR 30A (US 98) Back Beach Rd to Nof Westbay Icww Bridge
SR 79 from West Baybridge to Washington County Line
CR 3026 Cherry St from SR 30A (US 98) Tyndall PKWY to CR 2315 Star Ave
CR 3026 Cherry Street - West Side
Scott's Ferry Rd Over Bear Creek Bridge No. 464419
East Ave from Port Entrance to S of SR 30 (US 98B) 5TH Street
SR 390 Over Mill Bayou Bridge No. 460020
SR 368 23RD Street from US 98 Flyover to SR 390 St Andrews BLVD
SR 30 (US 98) Over St Andrews Bay Icww Bridge No. 460019
CR 2302 Bridge Street Over Fanning Bayou Bridge No. 460024
SR 20 Over Econfinacreek, Bridge No. 460037AND 460034
SR 77 from 23RD Street to CR 2312 Baldwin Road
SR 75 (US 231) at SR 20 Intersection Safety Improvements
SR 75 (US 231) from CR 2301 to N Campflowersrd
SR 30 (US 98) Multi-use Path from Crooked Sound Drive to CR 386
SR 30 (US 98) Multi-use Path from Crooked Sound Drive to CR 386
SR 30/30-A (US 98) 15TH St from E of 23RD Stflyover to Jenks Ave
SR 75 (US 231) at Pipeline Road Intersectionimprovements
Berthe Ave from Forsythe Dr to Eagle Lake Way
SR 20 from SR 75 (US 231) to Calhoun County Line
SR 75 (US 231) from SR 30A (US 98) 15TH St to CR 2312 Baldwin Rd
SR 368 23RD St from SR 390 to SR 75 (US 231)
CR 389/EAST 12TH Street from SR 390 to Pennsylvania Avenue
SR 30 (US 98) Tyndall Parkway from Tram Rd to Hickory St
SR 388 from SR79 to East of Nwf Beaches Int'l Airport
Tennessee Avenue from 14TH Street to 5TH Street
SR 75 (US 231) at CR 388 Intersection Improvements
SR 75 (US 231) Froms of SR 20 to The Jackson County Line
Lake Drive from SR 30 (US 98) to S Berthe Avenue
CR 2321 from SR 77 to Deer Point Lake Dam Bridge - Ph Ii
Westbay PKWY from Walton Co Line to Western Edge of Bay Creek Dsap
SR 30 (US 98B) from SR 75 (US 231) Harrison Ave to N of Dupont Bridge
SR 30 (US 98) Over Navy BLVD Flyover Bridge No. 460111
SR 390 St Andrews BLVD from CR 2341 Jenks Ave to E of SR 77 Ohio Ave
CR 385 Frankford Ave from SR 390 St Andrews BLVD to Pacifica Lane
Robinson Bayou Bridge Refurbishment
Bayl Panama City Yard/locomotive Shop Track Improvement
SR 79 Over Icww at Westbay Bridge Nos 460077 & 460128
SR 390 at Harvard BLVD
SR 77 Mlk Boulevardfrom SR 30 (US 98B) to Bay Line Railroad
SR 30A (US 98) PC Beach PKWY from Christmas Tree Ln to E Powell Adams
SR 370 Gulf Coast PKWY from SR 30A (US 98) to CR 2315 Star Avenue
SR 22 at Callaway Elementary School
SR 30 (US 98) Over Phillips Inlet & Watson Bayou Br #460072, 073, 078
SR 77 from Bailey Bridge to North of Libertyavenue
SR 368 23RD Street from Realignment to W of SR 390 Beck Avenue
S Gay Ave from Boatrace Rd to Cherry St
Bay County Park & Ride Landscaping
Moylan Rd at SR 30 (US 98A) Front Beach Rd
SR 77 at CR 388
SR 30A (US 98) PC Beach Parkway from Mandy Lane E of Nautilius St.
Pipeline Rd Extension from W of Country Lakedr to Nehi Rd
Lynn Haven Elementary School Sidewalk Project - Ph I
No projects match.
FY is the state fiscal year, July to June, named for the year it ends (FY2027 = July 2026 to June 2027). FDOT's map layers don't give each phase's dollars; the full budget for each project is in FDOT's work program.
County and city road work
From the half-cent sales tax map829 county and city road jobs paid for by the sales tax are finished; 60 are in progress and 79 are next. The sales tax page has every job on a map, with what was promised.
| Project | Government | Status | Cost |
|---|---|---|---|
| 4th Street Reconstruction Design Resurfacing | City of Panama City | In progress (5%) | $1.2M |
| Scotts Ferry Road Bridge Replacement Bridge Repair | Bay County | In progress (30%) | $420K |
| Ashland Way Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Bay Parkway Phase III Capacity Improvement | Bay County | In progress (10%) | — |
| Big Oak Ln Resurfacing Resurfacing | City of Callaway | In progress (25%) | — |
| Blanche Dr Local Road Reconstruction | Bay County | In progress (90%) | — |
| Boat Race Rd Resurfacing Resurfacing | City of Callaway | In progress (25%) | — |
| Brewton Ln Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Cambridge Ct Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Cherry St Phase 2 Capacity Improvement | City of Panama City | In progress (54%) | — |
| Cherry St Utilities Capacity Improvement | City of Panama City | In progress (30%) | — |
| Cherry St Utilities Capacity Improvement | City of Panama City | In progress (81%) | — |
127 more in progress or next
| Project | Government | Status | Cost |
|---|---|---|---|
| Cherry Street Reabilitation Resurfacing | City of Callaway | In progress (15%) | — |
| David Ave Resurfacing | City of Springfield | In progress (35%) | — |
| Deep Bayou Dr Local Road Reconstruction | Bay County | In progress (90%) | — |
| E Lakeland Dr Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Emergency Generators Capacity Improvement | City of Springfield | In progress (50%) | — |
| Gilchrist Ave Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Halsey Cir Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Highpoint Rd Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Highpoint Rd Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Highpoint Rd Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Highpoint Rd Local Road Reconstruction | Bay County | In progress (90%) | — |
| Highpoint Rd Local Road Reconstruction | Bay County | In progress (90%) | — |
| Highway 2321 Resurfacing | Bay County | In progress (90%) | — |
| Jessica Ct Local Road Reconstruction | Bay County | In progress (90%) | — |
| Joan Avenue at North Lagoon Drive Intersection Improvements Intersection Improvement | Bay County | In progress (10%) | — |
| Lance St Repaving Resurfacing | City of Springfield | In progress (50%) | — |
| Morgan Rd Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Oak View Dr Local Road Reconstruction | Bay County | In progress (90%) | — |
| Rasch Rd Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Shady Dr Local Road Microsurfacing | Bay County | In progress (90%) | — |
| Sherman Avenue and 15th Street (US Highway 98) Intersection Improvements Intersection Improvement | Bay County | In progress (10%) | — |
| Star Avenue and US Highway 231 Intersection Improvements Intersection Improvement | Bay County | In progress (10%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility & Road Improvements Utility and Road Improvement | City of Springfield | In progress (35%) | — |
| Utility Improvements Capacity Improvement | City of Springfield | In progress (50%) | — |
| 13th Street Bridge Replacement Bridge Repair | Bay County | Next | — |
| 1st St Local Road Reconstruction | Bay County | Next | — |
| 26th Street Connector Road Capacity Improvement | Bay County | Next | — |
| 3rd St Local Road Reconstruction | Bay County | Next | — |
| 4th St Local Road Reconstruction | Bay County | Next | — |
| 5th St Local Road Reconstruction | Bay County | Next | — |
| Alvie Holmes Road Bridge Replacement Bridge Repair | Bay County | Next | — |
| Azalea Dr Local Road Reconstruction | Bay County | Next | — |
| Azalea Dr Local Road Reconstruction | Bay County | Next | — |
| Baker Ct Utility Improvements Capacity Improvement | City of Panama City | Next | — |
| Baldwin Road Widening Capacity Improvement | Bay County | Next | — |
| Bay Head Road at County Road 2301 Intersection Improvements Intersection Improvement | Bay County | Next | — |
| Bayou George Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Blue Springs Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Blue Springs Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Brandon Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Chelsea Dr Local Road Reconstruction | Bay County | Next | — |
| Cluster Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Coleridge Rd Local Road Reconstruction | Bay County | Next | — |
| Colony Bay Harbour Dr Resurfacing | City of Panama City Beach | Next | — |
| Commerce Dr Projected Resurfacing and Reconstruction | Bay County | Next | — |
| County Line Road Paving Dirt Road Stabilization | Bay County | Next | — |
| County Road 2301 Bridge Replacement Bridge Repair | Bay County | Next | — |
| Deerfield Ln Local Road Reconstruction | Bay County | Next | — |
| Del Mar Dr Local Road Reconstruction | Bay County | Next | — |
| Del Mar Dr Local Road Reconstruction | Bay County | Next | — |
| Del Mar Dr Local Road Reconstruction | Bay County | Next | — |
| Delwood Beach Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Dogwood St Resurfacing | City of Panama City Beach | Next | — |
| El Prado Pl Local Road Reconstruction | Bay County | Next | — |
| First Ave Local Road Reconstruction | Bay County | Next | — |
| First Ave Local Road Reconstruction | Bay County | Next | — |
| HIGHWAY 2321 Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Highway 2321 Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Highway 2321 Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Holley Ln Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Indian Bluff Dr Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Indian Bluff Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Ivydell Street Paving Dirt Road Stabilization | Bay County | Next | — |
| Jan Cooley Dr Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Jan Cooley Dr Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Klondyke Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| La Paloma Pl Local Road Reconstruction | Bay County | Next | — |
| Lake Pl Local Road Reconstruction | Bay County | Next | — |
| Magnolia Beach Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Marlin Ave Local Road Reconstruction | Bay County | Next | — |
| Marlin Ave Local Road Reconstruction | Bay County | Next | — |
| Mashburn Road Bridge Replacement Bridge Repair | Bay County | Next | — |
| Maude Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Mc Elvey Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Mc Elvey Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Mceachern St Local Road Reconstruction | Bay County | Next | — |
| Mills Ln Local Road Reconstruction | Bay County | Next | — |
| Northwood St Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Otter Creek Bridge Replacement Bridge Repair | Bay County | Next | — |
| Owenwood Road Paving Dirt Road Stabilization | Bay County | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pedestrian Safety, City Sidewalks Roadway Safety | City of Lynn Haven | Next | — |
| Pinecrest Road Bridge Replacement Bridge Repair | Bay County | Next | — |
| Placido Pl Local Road Reconstruction | Bay County | Next | — |
| Placido Pl Local Road Reconstruction | Bay County | Next | — |
| Plantation Dr Local Road Reconstruction | Bay County | Next | — |
| Riviera Dr Local Road Reconstruction | Bay County | Next | — |
| Scenic Dr Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Scott Road Bridge Replacement Bridge Repair | Bay County | Next | — |
| Steel Field Road Paving Dirt Road Stabilization | Bay County | Next | — |
| Sundial Ct Resurfacing | City of Panama City Beach | Next | — |
| Venado Pl Local Road Reconstruction | Bay County | Next | — |
| Waverly St Projected Resurfacing and Reconstruction | Bay County | Next | — |
| West End Dr Local Road Reconstruction | Bay County | Next | — |
| Wood Cir Projected Resurfacing and Reconstruction | Bay County | Next | — |
| Yukon Rd Projected Resurfacing and Reconstruction | Bay County | Next | — |
Who builds the state's roads here
FDOT contracts since 2016| Contractor | Contracts | Under way | State contracts | Paid by local governments |
|---|---|---|---|---|
| Scott Bridge Company, Inc. | 1 | 1 | $343.9M | — |
| Phoenix Construction Services | 6 | 4 | $219.7M | $16.5M |
| Superior Construction Company Southeast, LLC | 2 | — | $128.5M | — |
| Anderson Columbia Co. | 11 | — | $114.7M | $20.0M |
| C.W. Roberts Contracting | 13 | 2 | $100.2M | $32.5M |
| Roberts and Roberts | 8 | 3 | $45.2M | $41.7M |
| Atlantic Specialty Insurance Company | 1 | — | $28.7M | — |
| Murphree Bridge Corporation | 3 | 2 | $17.2M | — |
| RJ Gorman Contracting, LLC | 1 | 1 | $14.8M | $9.1M |
| Ingram Signalization, Inc. | 7 | 1 | $5.3M | $10.2M |
| Traffic Control Devices, LLC | 1 | — | $4.3M | — |
| F & W Construction Company, Inc. | 2 | — | $3.6M | — |
| RAM Construction Services of Michigan, Inc. | 2 | — | $3.6M | — |
| Piney Grove Nursery and Landsca | 4 | 2 | $3.5M | — |
| Southern Road & Bridge, LLC | 3 | — | $2.8M | — |
Each name links to a profile with its local contracts, payments and campaign gifts. "Paid by local governments" adds every local payment record on the site for the same company, for comparison.
Finished state contracts since 2016 (68)
| Project | Contractor | Finished | Amount |
|---|---|---|---|
| Panama Operations Routine Maintenance - Routine Maintenance | Atlantic Specialty Insurance Company | Jun 2027 | $28.7M |
| SR 30 (US 98) Over St. Andrews Baybridge Nos. 460112 & 4601 13 - Bridge-repair/rehabilitation | Southern Road & Bridge, LLC | Apr 2026 | $1.5M |
| SR 30/30-A (US 98) 15TH St from E of 23RD Stflyover to Jenks Ave - Resurfacing | C.W. Roberts Contracting | Apr 2026 | $11.4M |
| SR 392A Hutchison BLVD from SR 30 (US 98A) to SR 30 (US 98A) - Resurfacing | Anderson Columbia Co. | Feb 2026 | $14.0M |
| SR 390 from 34TH Place to N of Jenks Ave Landscaping - Landscaping | Piney Grove Nursery and Landsca | Nov 2025 | $1.3M |
| SR 79 from West Baybridge to Washington County Line - Resurfacing | C.W. Roberts Contracting | Nov 2025 | $14.9M |
| SR 30 (US 98) from Walton County Line to Gulf County Line - ITS Communication System | Traffic Control Devices, LLC | Oct 2025 | $4.3M |
| SR 75 (US 231) from CR 2301 to N Campflowersrd - Resurfacing | Anderson Columbia Co. | Oct 2025 | $14.3M |
| SR 30 (US 98) Elevated Roadway E to W of Tyndall Afb Entrance - Interchange: add lanes | Anderson Columbia Co. | Oct 2025 | $22.5M |
| SR 30 (US 98) from W of Canal PKWY to Gulf County Line - Resurfacing | C.W. Roberts Contracting | Sep 2025 | $2.5M |
| SR 390 Beck Avenue @ 19TH Street Intersection - Traffic Sign Al Update | Ingram Signalization, Inc. | Jun 2025 | $988K |
| SR 75 (US 231) Over Bayou George Bridge No. 460079 - Bridge- Repair/rehabilitation | Bridge Masters Construction, LLC | Jun 2025 | $112K |
| SR 30 (US 98) @ SR 368 23RD St Intersection Landscaping - Landscaping | Piney Grove Nursery and Landsca | Apr 2025 | $887K |
| SR 30A (US 98) Pcb Parkway from Walton County Line to Heathe R Drive - Resurfacing | Anderson Columbia Co. | Jan 2025 | $20.2M |
| CR 389/EAST 12TH Street from SR 390 to Pennsylvania Avenue - Pave shoulders | American Sand & X-Cavation, Inc. DBA American Sand & Asphalt | Jan 2025 | $2.1M |
| SR 30A (US 98) PC Beach PKWY at Allison Ave - Safety Project | Ingram Signalization, Inc. | Aug 2024 | $852K |
| SR 390 St Andrews from Jenks Avenue to East of SR 77 Ohio Avenue - Add Lanes & Reconstruct | Phoenix Construction Services | May 2024 | $32.4M |
| SR 75 (US 231) @ CR 2327 Transmitter Road Intersection - Add Turn Lane(s) | Roberts and Roberts | Apr 2024 | $2.1M |
| Clara Ave from SR 30 Front Beach Rd to SR 30A (US 98) Back Beach Rd - Sidewalk | Rogar Management & Consulting of Florida LLC | Apr 2024 | $557K |
| SR 75 (US 231) from CR 2293 Titus Rd to CR 2315 Star Ave - S Afety Project | Ingram Signalization, Inc. | Apr 2024 | $943K |
| SR 388 from SR 79 to E of Nwf Beaches Intl Airport - Add lanes and reconstruct | Superior Construction Company Southeast, LLC | Jan 2024 | $55.3M |
| Airport Rd @ 19TH Street Intersection - Intersection Improve Ment | C.W. Roberts Contracting | Jan 2024 | $1.8M |
| SR 79 from SR 30A (US 98) Back Beach Rd to Nof Westbay Icww Bridge - Resurfacing | Anderson Columbia Co. | Dec 2023 | $7.3M |
| SR 75 (US 231) from SR 30 (bus 98) 6TH St to SR 30A (US 98) 15TH St - Resurfacing | Anderson Columbia Co. | Oct 2023 | $3.0M |
| SR 30 (US 98) 18TH St from Baltimore Ave to Grant Ave - Safety Project | Ingram Signalization, Inc. | Sep 2023 | $288K |
| SR 20 from Washington County Line to SR 77 - Resurfacing | C.W. Roberts Contracting | Aug 2023 | $4.5M |
| SR 30 (US 98) Over St Andrews Bay Br. Nos. 460112 & 460113 - Bridge-repair/rehabilitation | RAM Construction Services of Michigan, Inc. | Jun 2023 | $3.2M |
| SR 30 (US 98B) from Morris Dr to Municipal Park Entrance - S Idewalk | Rogar Management & Consulting of Florida LLC | May 2023 | $928K |
| SR 390 E 14TH Street from E of SR 77 Ohio Ave to SR 75 (US 2 31) - Resurfacing | Roberts and Roberts | Apr 2023 | $7.3M |
| SR 77 from North Baybridge to CR 2300 Landscaping - Landsca Ping | Rotolo Consultants, Inc. | Feb 2023 | $300K |
| SR 20 from SR 77 to SR 75 (US 231) - Resurfacing | Anderson Columbia Co. | Feb 2023 | $6.2M |
| SR 388 Over Crooked Creek Br No 460051 - Bridge-repair/rehab Ilitation | M & J Construction Company of Pinellas County, Inc. | Dec 2022 | $500K |
| SR 30 (usb 98) from SR 30A (US 98) to W of SR 75 (US 231) Harrison Ave - Resurfacing | C.W. Roberts Contracting | Nov 2022 | $4.1M |
| SR 390 (St Andrews Blvd) Hurricane Irma Mandtory Work Stoppa Ge Idel Labor & Equipment | Phoenix Construction Services | Apr 2022 | $18.5M |
| SR 77 from End of Curb & Gutter Southport to S of Washington Co. Line - Resurfacing | Anderson Columbia Co. | Nov 2021 | $13.2M |
| CR 22A Bob Little Rd from SR 30 (US 98B) E Hwy 98 to Lakedr Ive - Sidewalk | BCL Civil Contractors | Jun 2021 | $679K |
| CR 389 East Avenue Over Watson Bayou Bridge No. 464201 - Bridge Replacement | F & W Construction Company, Inc. | May 2021 | $2.7M |
| SR 30 (US 98) Front Beach Road from Watkins St to Kilgore Rd - Safety Project | Ingram Signalization, Inc. | May 2021 | $778K |
| SR 30 (US 98) @ SR 368 23RD Street Intersection Phase I & Ii - Add Lanes & Reconstruct | Superior Construction Company Southeast, LLC | Mar 2021 | $73.2M |
| SR 30 (US 98) Hathaway Bridge Bridge No. 460112 & 460113 - E Mergency Operations | Paul Patrick Electric, Inc. | Oct 2020 | $232K |
| SR 75 (US 231) @ 19TH St Intersection - Add Right Turn Lane( S) | C.W. Roberts Contracting | Aug 2020 | $467K |
| SR 368A Collegiate Dr from W of Moody Avenue to SR 368 23RD Street - Widen/resurface Exist Lanes | C.W. Roberts Contracting | Jun 2020 | $720K |
| SR 392 A Hutchison BLVD @ Clara Avenue Intersection - Traffic Signals | World Fiber Technologies, LLC. | Jun 2020 | $811K |
| SR 30 Front Beach Road from E Lakeshore Drive to Portside Drive - Sidewalk | David Taylor Construction | Apr 2020 | $810K |
| SR 30A (US 98) Tyndall PKWY from E of CR 2327 to SR 30 (US 9 8B) - Resurfacing | Roberts and Roberts | Apr 2020 | $5.9M |
| SR 75 (US 231) Bayou George Bridge No. 460028 & 460079 - Bri Dge-repair/rehabilitation | Orlando R&B, LLC | Mar 2020 | $764K |
| SR 77 Holding Pond Fence Repairs Due to Hurricane Michael - Emergency Operations | T & M Lawn-Fence Service Inc | Feb 2020 | $91K |
| SR 30 (US 98) Over St Andrews Bay Icww Bridge No. 460019 - B Ridge-repair/rehabilitation | Southern Road & Bridge, LLC | Jan 2020 | $551K |
| SR 75 (US 231) Harrison Ave Replace Overhead Sign Structure NO.46S517 - Emergency Operations | Ingram Signalization, Inc. | Jan 2020 | $291K |
| SR 30 (usb 98) 6TH St Watson Bayou Bridge No. 460073 - Bridg E-repair/rehabilitation | Pneumatic Concrete Co., Inc. | Nov 2019 | $498K |
| SR 30 (US 98) Hathaway Bridge Bridge No. 460112 & 460113 - E Mergency Operations | Pigott Asphalt and Sitework LLC | Oct 2019 | $281K |
| 36TH Street Over Bayou Bridge No. 466001 - Bridge Replacement | Murphree Bridge Corporation | Apr 2019 | $1.5M |
| SR 79 from SR 388 Don Johnson Mem Hwy to Wash C.o. Line Land Scaping - Landscaping | Valdez, Frankie Co., Inc. | Mar 2019 | $462K |
| SR 30 (US 98) Phillips Inlet Bridge Nos. 460072 & 460078 - B Ridge-repair/rehabilitation | RAM Construction Services of Michigan, Inc. | Feb 2019 | $344K |
| SR 30A (US 98) PC Beach Parkway @ Cauley Avenue Intersection - Add Turn Lane(s) | Roberts and Roberts | Jul 2018 | $2.2M |
| SR 30 (US 98) from Dupont Bridge to Gulf County Line - Resur Facing | Anderson Columbia Co. | Jun 2018 | $8.9M |
| SR 30 (alt US 98) from Portside Drive to SR 79 - Sidewalk | Orlando R&B, LLC | Mar 2018 | $392K |
| SR 30 (US 98) Front Beach Rd @ CR 392 Thomas Drive Intersection - Lighting | Murdock Investments, LLC DBA Griffin Traffic Signals | Mar 2018 | $141K |
| SR 391 Airport Road from Harrison Avenue to SR 390 St Andrew S BLVD - Resurfacing | C.W. Roberts Contracting | Jan 2018 | $1.1M |
| SR 30 (US 98) Over St Andrews Bay Icww Bridge No. 460019 - B Ridge-repair/rehabilitation | H.G. Harders & Sons | Nov 2017 | $1.7M |
| Arthur Drive Over Lynn Haven Bayou Bridge No. 464514 - Bridg E Replacement | F & W Construction Company, Inc. | Aug 2017 | $937K |
| SR 30A (US 98) Back Beach Rd @ SR 79 Intersection - Intersec Tion Improvement | Anderson Columbia Co. | Jul 2017 | $1.1M |
| SR 391 Airport Road from SR 75 (US 231) to Harrison Avenue - Bike Path/trail | C.W. Roberts Contracting | Jan 2017 | $503K |
| SR 30 (US 98) Thomas Drive Flyover Landscaping Landscaping | Bay Landscape & Palm Service LL | Nov 2016 | $280K |
| SR 79 Over Westbay Bridge No. 460077 - Bridge-repair/rehabi Litation | Southern Road & Bridge, LLC | Sep 2016 | $762K |
| SR 30A (US 98) 15TH from W of Jenks Avenue to SR 389 East Avenue - Resurfacing | Anderson Columbia Co. | Aug 2016 | $4.0M |
| SR 77 Vws Bay County W/pull Off Scale - Mcco Weigh Station S Tatic/wim | Roberts and Roberts | Aug 2016 | $1.5M |
| SR 22 from SR 30 (US 98B) to West of CR 2315 Star - Resurfacing | C.W. Roberts Contracting | Jun 2016 | $3.0M |
Where this comes from
- State contracts: FDOT's public map of every construction and maintenance contract, read weekly. FDOT leaves some old contracts marked active; a contract counts as under way here only when FDOT's map flags it active, and as finished once its final acceptance or estimated finish date has passed.
- Five-year plan: FDOT's current adopted work program layers, read weekly: each project's phases and the fiscal years they're funded in.
- County and city work: the county's half-cent sales tax project map, the same data as the sales tax page.
- Lane closures change by the hour, so they aren't copied here; FL511 has them live.
- Data: road-contracts (CSV) · road-work-program (CSV) · sales-tax-projects.